Context

The UN agency's medical centre in Cairo supports UN humanitarian activities that cannot tolerate unplanned outages. Repeated grid instability across 2024 disrupted clinical scheduling and put refrigerated medical inventory at risk. Nash was engaged to design and deliver a continuity-grade power solution sized to the facility's critical load.

Challenge

  1. 1Maintain continuous power to clinical refrigeration, IT systems, and lighting through extended grid events.
  2. 2Work within a constrained rooftop and courtyard footprint shared with existing MEP plant.
  3. 3Deliver a structural solution that integrated visually with the facility, including a shaded outdoor waiting area.
  4. 4Coordinate civil, electrical, and PV scopes under a single procurement and schedule.

Solution

Scope

Design, supply, and installation of a 20 kW off-grid solar PV system with battery storage, structural pergola, electrical tie-in, and monitoring. Includes single-line diagrams, structural calculations, as-built documentation, and operator training.

Technologies

  • Tier-1 monocrystalline PV modules
  • MUST-series hybrid inverter configured for off-grid operation
  • Battery bank sized for the facility's critical-load continuity profile (chemistry per project specification)
  • Galvanized steel pergola structure
  • Remote monitoring and yield telemetry

Engagement model

Single-source design-build under the client's procurement framework, with weekly status reporting and a single Nash account lead coordinating civil, electrical, and PV trades.

Duration

Approximately 10 weeks from kickoff to commissioning.

Outcome

Quantitative results

  • 20 kW PV capacity installed with monitored yield against design model.
  • Multi-hours critical-load reserve through battery storage, sized to the facility's continuity-grade load profile.
  • Zero clinical-day disruption attributable to power events post-commissioning.

Qualitative

The pergola-integrated canopy added a shaded outdoor area used by patients and staff, turning a continuity investment into a visible facility improvement.

Artifacts available on request

  • Single-line electrical diagram
  • Structural calculations and pergola drawings
  • Yield model and as-built test report
  • Operator handover pack

Nash shares engagement artifacts with qualified buyers under NDA. Request a copy and we will reply within one business day.

Request artifacts

Related projects

Software & Technology

Full HQ Renovation for Bashar Soft — Ground and Basement Floors

End-to-end renovation of Bashar Soft's headquarters across ground and basement floors, integrating electrical, low-current, ICT, and facility scopes under a single delivery.

Read case study

BPO & Contact Centers

Call Center Infrastructure Deployment for Sky CX

End-to-end call center infrastructure — servers, enterprise network switching, call center manager platform, full configuration, and ongoing services.

Read case study

Plan your next project with Nash.

Tell us what you're scoping. A senior integrator will respond within one business day.